    What is the conduit fill limit for low-voltage cable?

    The NEC Chapter 9 Table 1 percentages apply: 53% for one cable, 31% for two, and 40% for three or more, with 60% allowed in a nipple of 24 inches or less. ANSI/TIA-569 and Article 800/770 also recommend a 40% ceiling for communications pathways. This tool applies the Table 1 value matching your cable count.

    Run the numbers for your project

    Use the Low-Voltage Conduit Fill Calculator (%) to get an exact answer for your inputs.

    Open the calculator

    Related questions

    Estimates and general guidance only. Verify against your local code and AHJ before any installation. Gas, electrical, and refrigerant work is hazardous to untrained users.