Panel Replacement & Load Re-Balance
Scope
Replace a residential service panel — typically swapping a legacy panel (FPE Stab-Lok, Zinsco, or end-of-life 60 A fuse) for a current code-compliant 100 A or 200 A panel, and re-balance branch circuits across the two hot legs.
Safety
The line side of a residential panel is energized by the utility — you cannot de-energize it from inside the house. This work REQUIRES a utility cutoff (meter pull or service disconnect). Most jurisdictions also require this be done by a licensed electrician under permit. This guide exists as preparation reference for homeowners coordinating with their electrician, NOT as a DIY procedure.
Pre-Check
10 items · complete before you startSteps
Plan the swap and re-balance
- Inventory every existing branch circuit: amp rating, conductor size, room/load served
- Note any AFCI / GFCI requirements triggered by NEC 2023 §210.8 and §210.12 for the new panel
- Plan circuit placement to balance load across the two 120 V legs — sum amperage on Leg A ≈ sum amperage on Leg B
- Put pairs of related loads on opposite legs (e.g. kitchen + bath both heavy on each leg)
- Identify any multi-wire branch circuits (MWBC) — must land on a 2-pole or handle-tied breaker per NEC §210.4(B)
- NEC §408.40 — equipment grounding bus in panelboards.
- NEC §230.67 — surge protective device required at dwelling-unit service equipment (NEC 2023).
Utility cutoff — coordinate with the utility
- The utility pulls the meter or opens the service disconnect — this is the only way to de-energize the line side
- A licensed electrician witnesses the cutoff and verifies zero energy at the line lugs
- Lockout/tagout is applied per utility protocol; bypass is utility-prosecution territory
- Confirm the utility tag and seal — DO NOT cut a utility seal yourself
- Cutting a utility seal is a criminal offense and can result in disconnection plus prosecution.
- Working hot on the line side has killed experienced electricians. There is no shortcut.
Document and remove existing circuits
- With the panel de-energized and verified, photograph every wire connection
- Label each branch conductor with its destination (use printed tape, not Sharpie that wipes off)
- Disconnect each branch one at a time, working from top to bottom
- Disconnect the neutral bus and ground bus connections, labeling as you go
- Disconnect the main service conductors (line side) — the utility witness verifies these are dead
Remove the old panel; mount the new
- Remove the old enclosure — note the existing knockouts and conduit entries
- Mount the new panel: same location is simplest; relocation requires re-routing all conductors
- Re-use existing conduit and weatherhead where possible
- Bond the new enclosure to the grounding electrode system per NEC §250.50 — water pipe + ground rod(s) + Ufer if available
- Install service-entrance surge protection per NEC §230.67 (required as of NEC 2023)
- NEC §250.50 — bonding all available grounding electrodes (water pipe ≥10 ft contact, ground rods 8 ft × 2, Ufer / concrete-encased electrode).
- NEC §250.104(A) — bond metallic water piping to the service equipment ground.
- NEC §110.26(A) — working clearance: 36 in depth, 30 in width, 6 ft 6 in height in front of the panel.
Land branch circuits with re-balance
- Land each branch hot on the breaker space that balances total load across Legs A and B
- Multi-wire branch circuits land on a 2-pole or handle-tied 2-single-pole breaker (NEC §210.4(B))
- Each grounded (neutral) conductor lands on an individual neutral bus terminal — no doubling (NEC §408.41)
- Each equipment grounding conductor lands on the ground bus — most panel manufacturers allow two grounds per terminal; verify the panel label
- AFCI and GFCI requirements per NEC 2023 §210.8 and §210.12 — install AFCI/GFCI breakers as required for each circuit
- Torque every lug to the panel's spec sticker
- Aluminum branch-circuit conductors (mid-1960s to mid-1970s "old technology aluminum") require Co/Alr-rated devices and anti-oxidation compound. If you find aluminum branch wiring, scope expands — discuss with your electrician.
Restore service and verify
- Reinstall the deadfront cover
- Utility re-installs the meter and re-energizes
- Set the main breaker, then restore each branch one at a time
- Verify 240 V between hot legs at the bus; verify 120 V each leg to neutral
- Walk every circuit: test each receptacle, switch, and appliance for normal operation
- Verify AFCI / GFCI test buttons trip and reset on every required circuit
Inspection sign-off
- Leave the deadfront OFF for the AHJ inspector — they verify torque, conductor sizing, grounding/bonding, and clearance
- Have the load calc, panel directory, and any SCCR labeling visible
- Document the final-passed inspection — required for some insurance carriers