Skip to main content
    All guides
    ElectricalAdvanced

    Panel Replacement & Load Re-Balance

    Time
    360–720 min
    Steps
    7
    Pre-check
    10 items
    Skill
    Advanced

    Scope

    Replace a residential service panel — typically swapping a legacy panel (FPE Stab-Lok, Zinsco, or end-of-life 60 A fuse) for a current code-compliant 100 A or 200 A panel, and re-balance branch circuits across the two hot legs.

    Safety

    Read before starting

    The line side of a residential panel is energized by the utility — you cannot de-energize it from inside the house. This work REQUIRES a utility cutoff (meter pull or service disconnect). Most jurisdictions also require this be done by a licensed electrician under permit. This guide exists as preparation reference for homeowners coordinating with their electrician, NOT as a DIY procedure.

    Pre-Check

    10 items · complete before you start
    0 / 44 complete

    Steps

    01

    Plan the swap and re-balance

    • Inventory every existing branch circuit: amp rating, conductor size, room/load served
    • Note any AFCI / GFCI requirements triggered by NEC 2023 §210.8 and §210.12 for the new panel
    • Plan circuit placement to balance load across the two 120 V legs — sum amperage on Leg A ≈ sum amperage on Leg B
    • Put pairs of related loads on opposite legs (e.g. kitchen + bath both heavy on each leg)
    • Identify any multi-wire branch circuits (MWBC) — must land on a 2-pole or handle-tied breaker per NEC §210.4(B)
    Code notes
    • NEC §408.40 — equipment grounding bus in panelboards.
    • NEC §230.67 — surge protective device required at dwelling-unit service equipment (NEC 2023).
    02

    Utility cutoff — coordinate with the utility

    • The utility pulls the meter or opens the service disconnect — this is the only way to de-energize the line side
    • A licensed electrician witnesses the cutoff and verifies zero energy at the line lugs
    • Lockout/tagout is applied per utility protocol; bypass is utility-prosecution territory
    • Confirm the utility tag and seal — DO NOT cut a utility seal yourself
    ⚠ Warnings
    • Cutting a utility seal is a criminal offense and can result in disconnection plus prosecution.
    • Working hot on the line side has killed experienced electricians. There is no shortcut.
    Continue Gate:Have you (1) turned off the breaker, (2) tested your non-contact tester on a KNOWN-LIVE source, (3) verified zero energy at the conductors you are about to touch, and (4) re-tested the tester on the known-live source to confirm it still works? (NFPA 70E §120.5)
    03

    Document and remove existing circuits

    • With the panel de-energized and verified, photograph every wire connection
    • Label each branch conductor with its destination (use printed tape, not Sharpie that wipes off)
    • Disconnect each branch one at a time, working from top to bottom
    • Disconnect the neutral bus and ground bus connections, labeling as you go
    • Disconnect the main service conductors (line side) — the utility witness verifies these are dead
    04

    Remove the old panel; mount the new

    • Remove the old enclosure — note the existing knockouts and conduit entries
    • Mount the new panel: same location is simplest; relocation requires re-routing all conductors
    • Re-use existing conduit and weatherhead where possible
    • Bond the new enclosure to the grounding electrode system per NEC §250.50 — water pipe + ground rod(s) + Ufer if available
    • Install service-entrance surge protection per NEC §230.67 (required as of NEC 2023)
    Code notes
    • NEC §250.50 — bonding all available grounding electrodes (water pipe ≥10 ft contact, ground rods 8 ft × 2, Ufer / concrete-encased electrode).
    • NEC §250.104(A) — bond metallic water piping to the service equipment ground.
    • NEC §110.26(A) — working clearance: 36 in depth, 30 in width, 6 ft 6 in height in front of the panel.
    05

    Land branch circuits with re-balance

    • Land each branch hot on the breaker space that balances total load across Legs A and B
    • Multi-wire branch circuits land on a 2-pole or handle-tied 2-single-pole breaker (NEC §210.4(B))
    • Each grounded (neutral) conductor lands on an individual neutral bus terminal — no doubling (NEC §408.41)
    • Each equipment grounding conductor lands on the ground bus — most panel manufacturers allow two grounds per terminal; verify the panel label
    • AFCI and GFCI requirements per NEC 2023 §210.8 and §210.12 — install AFCI/GFCI breakers as required for each circuit
    • Torque every lug to the panel's spec sticker
    Service Panel Layout (Main & Buses)· NEC Wiring
    ⚠ Warnings
    • Aluminum branch-circuit conductors (mid-1960s to mid-1970s "old technology aluminum") require Co/Alr-rated devices and anti-oxidation compound. If you find aluminum branch wiring, scope expands — discuss with your electrician.
    06

    Restore service and verify

    • Reinstall the deadfront cover
    • Utility re-installs the meter and re-energizes
    • Set the main breaker, then restore each branch one at a time
    • Verify 240 V between hot legs at the bus; verify 120 V each leg to neutral
    • Walk every circuit: test each receptacle, switch, and appliance for normal operation
    • Verify AFCI / GFCI test buttons trip and reset on every required circuit
    07

    Inspection sign-off

    • Leave the deadfront OFF for the AHJ inspector — they verify torque, conductor sizing, grounding/bonding, and clearance
    • Have the load calc, panel directory, and any SCCR labeling visible
    • Document the final-passed inspection — required for some insurance carriers