Water HeatersAdvanced
Install Tankless Water Heater
Time
360–600 min
Steps
7
Pre-check
5 items
Skill
Advanced
Scope
Mount, plumb, vent, and commission a gas or electric tankless water heater for endless on-demand hot water, with correct gas, water, and venting hookups.
Safety
Read before starting
Permits and code may be required; verify gas/electrical capacity and venting; follow manufacturer precisely.
Pre-Check
5 items · complete before you start0 / 26 complete
Steps
Layout & Mount
- Mark mounting points at required clearances
- Install mounting bracket/anchors per manual
- Hang unit and verify plumb/level
Code notes
- Size the unit per ACCA Manual J/S (IRC §M1401.3). Rule-of-thumb sizing is not code-compliant for replacement permits in most AHJs.
✅Continue Gate:Mounting secure and clearances met?
Venting (Gas units)
- Assemble vent per listed system; observe orientation and slope
- Terminate with clearances to openings
- Seal per manufacturer; support vent runs
✅Continue Gate:Venting installed to listing and code?
Water Connections
- Install isolation valve kit
- Cold inlet with screen; hot outlet to manifold
- Install pressure relief and expansion as required
Code notes
- TPR discharge piping per IPC §504.6: full-size of valve outlet, single device, gravity flow, no traps/valves/threaded end, terminate 6″ max above floor or waste-receptor flood rim and ≥2× pipe diameter, pressure rating ≥100 psi @ 180°F.
- Closed systems (PRV, check, or backflow on cold inlet) require a thermal-expansion tank — IPC §607.3 / UPC §608.
✅Continue Gate:Isolation/relief in place; no cross-connection?
Fuel/Electrical
- Gas: size and connect line; leak-test with detector/soap
- Electric: land conductors per diagram; verify ground/bond
- Route condensate to approved drain (condensing)
Code notes
- NFPA 54 / 2024 IFGC gas leak test: medium is air, nitrogen, CO₂, or inert gas — never fuel gas or oxygen. Test pressure ≥1.5× working pressure but ≥3 psig; hold ≥10 min. Sediment trap (drip leg) required upstream of each appliance.
- Electric tankless: NEC 422 dedicated branch circuit; size per nameplate amperage.
✅Continue Gate:No leaks; wiring correct; condensate handled?
Flush & Debris Protection
- Flush lines prior to startup
- Install inlet screen/filters
- Consider scale inhibitor per water hardness
✅Continue Gate:Debris cleared; protection installed?
Commissioning
- Power ON; run startup routine per manual
- Set temperature; run multiple fixtures to stabilize
- Check error codes; verify venting draft and combustion (gas)
✅Continue Gate:Stable operation without faults?
Owner Handover
- Demonstrate isolation/flush ports usage
- Review descaling schedule
- Document serial and installation data