Skip to main content
    All guides
    Water HeatersAdvanced

    Replace Water Heater

    Time
    240–480 min
    Steps
    10
    Pre-check
    5 items
    Skill
    Advanced

    Scope

    Remove an old tank water heater and install and commission a new gas or electric unit, with proper water, fuel, and venting connections plus a full leak test.

    Safety

    Read before starting

    Shut off gas/power and water; verify no gas leaks; follow manufacturer and local code; permit may be required.

    Pre-Check

    5 items · complete before you start
    0 / 36 complete

    Steps

    01

    Secure Utilities & Prep

    • Turn off breaker (electric) or set gas valve to OFF
    • Close cold water inlet valve
    • Attach hose to drain; route to safe drain
    • Open hot water faucet to relieve pressure
    Continue Gate:Power/gas off and pressure relieved?
    02

    Drain and Disconnect

    • Open drain valve; drain tank fully
    • Disconnect gas flex/electrical whip (as applicable)
    • Disconnect vent (gas) and water connections
    Continue Gate:Tank empty and all lines disconnected?
    03

    Remove Old Tank

    • Remove straps and pan connections
    • Two-person lift or dolly removal
    • Inspect platform/pan and floor condition
    04

    Place New Tank

    • Position pan and tank with clearances per manual
    • Align T&P discharge, vent (gas), and water connections
    • Install earthquake straps (where required)
    Continue Gate:Clearances and orientation correct?
    05

    Connect Water

    • Install dielectric unions if needed
    • Connect cold inlet and hot outlet with proper fittings
    • Use thread sealant/tape per fitting type
    Continue Gate:Joints aligned; no cross-threading?
    06

    Venting (Gas)

    • Rebuild vent with proper slope and materials
    • Maintain required clearances
    • Secure joints with listed connectors
    Continue Gate:Venting secure and code-compliant?
    07

    Fuel/Electrical

    • Gas: connect flex with approved sealant; leak-test with soap solution
    • Electric: connect whip per wiring diagram; verify ground/bond
    Continue Gate:No gas leaks; wiring correct?
    08

    Fill and Purge Air

    • Open cold inlet
    • Open nearest hot faucet until steady flow (no sputter)
    • Check for leaks at all joints
    Continue Gate:Tank full; air purged; joints dry?
    09

    Commissioning

    • Restore gas/power
    • Set thermostat (120°F typical)
    • For gas: follow lighting/ignition procedure and verify flame characteristics
    • Verify T&P valve operation briefly
    Continue Gate:Heat source active; normal operation observed?
    10

    Finalize & Educate

    • Label shutoffs and breaker
    • Review maintenance (anode check, flushing schedule)
    • Document install date, model/serial